Running Input Wiring; Setting Gate Open Direction Switches S2 And S3; Power Up Procedure; Figure 4. Gate Direction, Power Fail Option Switch Location - Chamberlain BG 3000-B1 Installation And Operation Instructions Manual

Barrier gate operator
Table of Contents

Advertisement

C.

RUNNING INPUT WIRING

1. Run wires from input components and Master/Slave conduits into control box.
2. For Master/Slave wiring, refer to Installation and Operation of Master/Slave Systems for
Series B1 Gate Operators Doc. No. 6001378.
Route but do not connect input wires at this time. If inputs are connected now, the gate operator
may activate at random during installation, potentially injuring installation personnel.
D.

SETTING GATE OPEN DIRECTION SWITCHES S2 AND S3

1. Gate opening direction is set by switch S2, located on the control board. The switch is sensed
only on power up, so it should be set when the power is off.
2. Ensuring power is off, set switch S2 to the left if the cabinet access door faces away from the
driveway (typical installation), or to the right if the access door faces the driveway (restricted
installation).
If the system was ordered with the Power Fail Operation option:
3. The power failure gate opening direction is set by switch S3, located next to switch S2 on the
control board. Set switch S3 to left to fully open (Fail Safe) or to right to fully close (Fail
Secure) the gate during power outage (typical installation).
E.

POWER UP PROCEDURE

1. Turn on circuit breaker that provides power to gate operator.
2. On Manual Input Terminal TB2, connect the STOP terminal to the COMMON terminal (see
Figure 5).
3. Turn on gate operator power switch and verify that the row of LEDs on the right side of the
controller board all turn on, then turn off sequentially, starting from the bottom. The only LEDs
that should remain on are Power ON, MAGLOCK, and CLOSE LIMIT or OPEN LIMIT, if one of
the limit switches are engaged.
NOTE:
If the LEDs do not follow this pattern, the controller board may not be working
correctly. Stop installation and call LiftMaster Technical Support for assistance.
Rev C

Figure 4. Gate Direction, Power Fail Option Switch Location.

Doc 6001287 (01-20284)
WARNING
7 of 40