9. The vent should not be situated so that the flue gases are directed towards brickwork,
siding, or other construction, in such a manner that may cause damage from heat or
condensate from the flue gases

8. Mounting Bracket

After a suitable installation location is chosen, verify that the mounting wall is properly
braced and strong enough to support the 110 pound weight of the unit when filled with
water.
NOTE: The boiler shall be installed such that the gas ignition system components are
protected from water and liquids in general (dripping,spraying, rain, etc) during
the appliance operation and service.
Use the paper template provided with the boiler to determine the location of the mounting
bracket. Securely mount the bracket to the wall using appropriate hardware for the particular
wall construction.
Mounting Steps:
1.
Tape the paper template to the wall in the chosen location. Be sure to level the
template.
2.
Pre-drill two holes in the center of the "oval" slots on the mounting bracket, sized for
the hardware being used.
3.
Mount the bracket to the wall. Be sure to level the bracket by adjusting the screw in
the vertical slot.
4.
Pre-drill the remaining hole in the mounting bracket and secure the final screw.
5.
Mark and drill the exhaust/intake pipe holes through the house. If you are using a
coaxial pipe system, drill the hole marked A (ø 4") in the drawing below and on the
paper template. If you are using a separate pipe system drill holes marked B and C (ø
3.25") shown below as well as on the paper template.
Remove paper template and hang boiler on bracket.
6.
Riva Plus Manual
Ø 3.1
Ø 3.1
B
C
Ø 4.0
A
1.9 2.9
7.9
15.8
2
5.6
4.5
1.4
0.6
3.9
10.1
1.4
6.5
2.5 2.6
4.6
7.9
A, B, C
8.9
6.9 gas
15.2
Condense
Figure 8.1