Finalizing the Installation

Steps for Finalizing the Installation

1.
Remove the glass (see page 39Error! Bookmark not defined.).
NOTE:
If using propane (LP) convert the appliance prior to installing the logs.
2.
We recommend you purge the gas line at this time (with the glass removed). This allows gas to be detected
once it enters the firebox, ensuring gas does not build up.
3.
Make sure the two accent light bulbs are in place.
NOTE: .Take care to not touch the bulb with your fingers (use a cloth or paper towel).
4.
Install the four AA batteries (see illustration below). The AA batteries act as a power backup in case the
household (AC) power goes out and are required for operation.
illustration below). Synchronize the transmitter to the IFC.
5.
Install the logs (see page 40).
6.
Replace the glass.
7.
Start the heater.
8.
Leak test all gas joints.
Travis Industries
(for qualified installers only)
Install three AAA batteries into the remote (see
4140613
100-01376

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

864 trv gsr2864 cleanface gsr2

Table of Contents