Restore To Normal Operation After "Total Off - GE LP 33 Series Operating Manual

60 – 80 – 100 – 120 kva 400 vac ce / series 2
Hide thumbs Also See for LP 33 Series:
Table of Contents

Advertisement

8.1.5 Restore to normal operation after "Total Off"

NOTE !
Make sure the UPS to be status of the activation of "Total Off", i. e. Q1 closed, Q2
open and the external battery fuses connected.
View of the synoptic diagram after pressing the "Total Off" key:
All Contactors are open.
Booster, Inverter and Static-Switch shutdown.
1.
Reset "Total Off".
Restore the command "Total Off" by entering the screen:
COMMANDS / RESET TOTAL OFF
LED Alarm is lit.
The load is supplied by the mains through the automatic
bypass.
The booster starts automatically.
The synoptic diagram must display the status "LOAD
SUPPLIED BY AUTOMATIC BYPASS".
2.
Insert the inverter by pressing "Inverter ON" ( I ) key.
Some seconds later the load will be transferred on inverter.
LED Alarm turn Off and the LED Operation must be lit.
The synoptic diagram must display the status "LOAD
SUPPLIED BY INVERTER".
Modifications reserved
OPM_LPS_33E_60K_M12_2GB_V010.doc
END OF PROCEDURE
Home\Commands
COMMANDS
RESET TOTAL OFF
REQUEST TOTAL OFF
Operating Manual LP 33 Series 60-80-100-120 kVA / S2
Page 78/103

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents