Download Print this page

Indoor Unit Installation - York YOCA-YOHA 12 Installation & Owner's Manual

Minisplit floor/ceiling air conditioner
Hide thumbs Also See for YOCA-YOHA 12:

Advertisement

CEILING INSTALLATION
Hanging arm
Chart 7
1. Remove the side board and the grille. (Refer to Chart 8)
(For models 48000 and 60000 Btu/h, do not remove the grille.)
Side board
Grille
Chart 8
2. Locate the hanging arm on the hanging screw bolt. (Refer to Chart 9)
Prepare the mounting bolts on the unit. (Refer to Chart 10)
S crew nut
Washer
Hanging
screw bolt
Mounting bolt (max. 40 mm)
Hanging arm
Chart 9
Chart 10
3. Hang the unit on the hanging arm by sliding backward. Securely tighten the
mounting bolts on both sides. (Refer to Chart 9)
Hanging
screw bolt
Hanging arm
Mounting bolt
D. Connecting point of refrigerant pipe
(D. gas side)
E. Connecting point of refrigerant pipe
(E. Liquid side)
Drain point
Chart 11
ATTENTION:
The gures above are based on model with 18000 Btu/h as rated
capacity, which may di er from the unit you purchased.
The dimension of the unit
Capacity
A
B
C
D
E
F
(Btu/h)
12000-24000 Btu/h
990
660
206
505
506
907
36000 Btu/h
1280
660
206
795
506
1195
48000-60000 Btu/h
1670
680
244
1070
450
1542
• Note: The dimension of 12000 Btu/h and 24000 Btu/h are the same
The dimension of 48000 Btu/h and 60000 Btu/h are the same
J422_EN.indd 2
Outdoor unit
YODA-YOJA 12 (50Hz)
YODA-YOJA 1 8 (50Hz)
285
750
845
313
301, 5
141, 5
560,1
62
530
110
YODA-YOJA 30-36 (50Hz)
YODA-YOJA 48-60 (50Hz)
990
336,4
400
940
181, 4
624
650
Model
YODA-YOJA 18
YODA-YOJA 24
YODA-YOJA 36
YODA-YOJA 48
YODA-YOJA 60
INSTALLATION IN THE FOLLOWING PLACES
MAY RESULT IN TROUBLE
8 13mm
Installation of the indoor unit in direct sun light.
Installation in the unit in wrong direction.
Installation of outdoor units too close or,
Installation of the indoor unit in a place where
blowing discharged air into each other.
there is an obstacle near the air inlet or outlet.
Installation of the outdoor unit in a place
Installation of the indoor unit at too high > 30 cm
exposed regularly to a strong wind.
a position.

INDOOR UNIT INSTALLATION

Installing Ø10 hanging screw bolts. (4 bolts)
• Please refer to the following gure for the distance measurement between the
G
H
screw bolts.
• Please install with Ø10 hanging screw bolts.
200
203
• The handling to the ceiling varies from the constructions, consult the construction
200
203
personnels for the speci c procedures.
200
240
1. The size of the ceiling to be handled ... ... do keep the ceiling at. Consolidate
the roof beam for possible vibration.
2. Cut o the roof beam.
3. Strengthen the place cut o , and consolidate the roof beam.
• Carry out the pipe and line operation in the ceiling after nishing the installation
of the main body. While choosing where to start the operation, determine the
direction of the pipes to be drawn out. Especially in case there is a ceiling, position
the refrigerant pipes, drain pipes, indoor & outdoor lines to the connection places
before hanging up the machine.
• The installation of hanging screw bolts.
Wooden construction
YODA-YOJA 24 (50Hz)
Put the square timber traversely over
the roof beam, then install the hanging
895
300
screw bolts. (Refer to Chart 1)
Timber over the beam
163
590
Roof beam
Ceiling
Hanging screw bolts
YODA-YOJA 36-60
(60Hz)
Chart 1
For Original concrete bricks
Use embedding screw bolt. (Refer to
Chart 3)
Steel bar
Embedding screw bolt
(Pipe hanging and embedding
screw bolt)
Chart 3
W
D
H
554
554
636
554
554
636
CONNECT THE DRAIN PIPE
554
554
840
740
740
852
740
740
852
1. Install indoor unit drain pipe
The outlet has PTI screw thread, Please use sealing materials and pipe sheath
( tting) when connecting PVC pipes.
Cautions
• The drain pipe of indoor unit must be heat insulated, or it will condense dew,
as well as the connections of the indoor unit.
• Hard PVC binder must be used for pipe connection, and make sure there is no
leakage.
• With the connection part to the indoor unit, please be noted not to impose
pressure on the side of indoor unit pipes.
• When the declivity of the drain pipe downwards is over 1/100, there should not
be any winding.
• The total length of the drain pipe when pulled out traversely shall not exceed
20m, when the pipe is over long, a prop stand must be installed to prevent
winding.
• Refer to the gures on the right for the installation of the pipes.
1.5m~2m
Bend
Insulating
Downward
material
declivity lower
than 1/100
2. Drainage test
• Check whether the drainpipe is unhindered
• New built house should have this test done before paving the ceiling.
3. Drain Elbow Installation
Fit the seal into the drain elbow, then insert the drain elbow into the base pan hole
of outdoor unit, rotate 90 ° to securely assemble them. Connect the drain elbow
with an extension drain hose (Locally purchased), in case of the condensate
draining o the outdoor unit during the heating mode. (Refer to Chart 17)
Seal
Drain elbow
The base pan hole
of outdoor unit
Chart 17
New concrete bricks
Inlaying or embedding the screw bolts.
(Refer to Chart 2)
Attaching wiring
1. The air conditioner should use separate power supply with rated voltage
2. The external power supply to the air conditioner should have ground wiring,
which is linked to the ground wiring of the indoor and outdoor unit.
(Blade shape insertion)
(Slide insertion)
3. The wiring work should be done by quali ed persons according to circuit
Chart 2
drawing.
4. A leakage protector should be installed according to the National Standard
concerning electrical appliance.
5. Be sure to locate the power wiring and the signal wring well to avoid cross-
disturbance and their contact with connecting pipe or stop valve body
6. The wiring attached to this air conditioner is 10m long. Be sure to prolong it
with wiring of the same type and proper length if necessary. Generally, do not
Steel roof beam structre
twist two wiring together unless the joint is soldered well and covered with
insulator tape.
Install and use directly the supporting
7. Do not turn on the power until you have checked carefully after wiring.
angle steel. (Refer to chart 4)
Hanging screw bolt
The Speci cation of Power
Supporting
TYPE
Hanging bolts
angle steel
Chart 4
PHASE
POWER
FREQUENCY AND VOLT
CIRCUIT BREAKER/FUSE
(A)
INDOOR UNIT POWER WIRING
(mm
GROUND WIRING
OUTDOOR UNIT
INDOOR/OUTDOOR
POWER WIRING
CONNECTING
WIRING
STRONG ELECTRIC
SIGNAL
(mm
2
)
WEAK ELECTRIC
SIGNAL
TYPE
PHASE
POWER
Put as deep as possible
FREQUENCY AND VOLT
(about 10cm)
CIRCUIT BREAKER/FUSE
(A)
S shape
INDOOR UNIT POWER WIRING
(mm
Downward declivity
lower than 1/100
VP30
GROUND WIRING
OUTDOOR UNIT
INDOOR/OUTDOOR
POWER WIRING
CONNECTING
WIRING
STRONG ELECTRIC
SIGNAL
(mm
2
)
WEAK ELECTRIC
SIGNAL
The base pan
hole of outdoor
Seal
Drain elbow
WIRING
.
12000~18000 Btu/h
24000-36000 Btu/h
36000-60000 Btu/h
(Cooling&Heating)
(Cooling&Heating)
(Cooling&Heating)
1-PHASE
1-PHASE
3-PHASE
220-240V~, 50Hz
220-240V~, 50Hz
380V 3N~, 50Hz
20/16
40/25
40/20
)
3x2.5
5x2.5
2
2.0
2.5
2.5
3x2.5
3x2.5
5x2.5
5x2.0
3x2.0
3x2.0
(3x2.0)
(2x2.0)
(2x2.0)
1-core sheild wire
2-core sheild wire
1x0.5mm
2
2x0.5mm
2
12000~18000 Btu/h
24000-36000 Btu/h
36000-60000 Btu/h
(Cooling Only)
(Cooling Only)
(Cooling Only )
1-PHASE
1-PHASE
3-PHASE
220-240V~, 50Hz
220-240V~, 50Hz
380V 3N~, 50Hz
40/25
40/20
40/25
2
)
3x2.5
3x2.5
5x2.5
2.0
2.0
2.0
3x2.0
5x2.0
3x2.0
1x2.0
1x2.0
Chart 1 8
10/30/07 11:01:25 AM

Advertisement

loading

This manual is also suitable for:

Yoca-yoha60Yoca-yoha 18Yoca-yoha 243648