Read this homeowner manual thoroughly and follow all
instructions carefully. Inspect all contents for shipping
damage and immediately inform your dealer if any damage
is found. Do not install any unit with damaged, incomplete,
or substitute parts. Check your packing list to verify that
all listed parts have been received. You should have the
following:
Fireplace (Firebox and Burner System)
Log Set
Rock Wool
Noncombustible Panel
IteMs RequIReD FOR InstaLLatIOn
Phillips Screwdriver
Hammer
Saw and/or saber saw
Measuring Tape
Electric Drill and Bits
Pipe Wrench
Noncombustible finishing material or dura-rock*
Caulking Material (noncombustible)
Fireplace Surround Material (noncombustible)
Piping Complying with Local Codes
Pipe Sealant Approved for use with Propane/LPG
(Resistant to sulfur compounds)
* Only used if desired to cover painted face other than using tiles
or marble. If tiles or marble are used around the face then the
non-combustible material is not needed.
Do not fill spaces around firebox with
insulation or other materials. this could
cause a fire.
cOLD cLIMate InsuLatIOn
If you live in a cold climate, seal all cracks
around your appliance, and wherever cold air
could enter the room, with noncombustible
material. It is especially important to insulate
the outside chase cavity between the studs
and under the floor on which the appliance
rests, if the floor is above ground level.
20300293
Framing Materials
Wall Finishing Materials
Level
Pliers
Square
Tee Joint
Resolution Direct Vent Gas Fireplace
FIReBOx FRaMInG
Firebox framing can be built before or after the appliance
is set in place. Refer to Figure 2 for firebox dimensions
and framing. Construct firebox framing following Figure
2 for your specific installation requirements. The framing
headers may rest on the top of the firebox standoffs. Do
not bring headers below top of standoffs. nOte: When
planning your framing and installation, keep in mind that
your gas line will come in on the right side of the box (as
you are facing it) and your electricity will come in on the
left side.
The firebox may be installed directly on a combustible floor
or raised on a platform of an appropriate height. When
the firebox is installed directly on carpeting, tile, or other
combustible material, other than wood flooring, the firebox
shall be installed on a metal or wood panel extending the
full width and depth of the enclosure.
unit framing is to be rectangular front to
back. Failure to do so will cause fire and
damage to property.