Dimensioning of the exhaust and air intake duct

The wall mounted boiler must be vented and supplied with combustion and
ventilation air as described in this section.
Ensure the vent and air piping and the combustion air supply comply with
these instructions regarding vent system, air system, and combustion air
quality.
Inspect fi nished vent and air piping thoroughly to ensure all are airtight and
comply with the instructions provided and with all requirements of applicable
codes.
Failure to provide a properly installed vent and air system may cause severe
personal injury or death.
Use only the material listed in Rinnai's vent documentation for vent pipe, and
fi ttings. Failure to comply could result in severe personal injury, death or
substantial property damage.
Installation must comply with local requirements and with the National Fuel
Gas Code, ANSI Z223.1 for U.S installations or CSA B 149.1 for Canadian
installations.
For closet and alcove installation, CPVC material (instead of PVC) must be
used in a closet/alcove structure. Failure to follow this warning could result
in fi re, personal injury, or death.
All vent pipes must be connected and properly supported, and the exhaust
must be pitched a minimum of a 1/4"/foot (21 mm/m) back to the boiler (to
allow drainage of condensate). Please refer to the venting manufacturer's
manual to see if a larger pitch is required for specifi c venting systems.
The venting system manufacturer's required venting pitch must always be
followed if larger than 1/4" (21 mm). Ubbink concentric condensing venting
requires a pitch of ¾"/foot (6mm/m).
Combustion air piping from the outside MUST must comply to the
requirements of the authority having jurisdiction or, in the absence of such
requirements, to the latest edition of the National Fuel Gas Code, ANSI
Z223.1/NFPA 54. In Canada, installation must be in accordance with the
requirements of CAN/CSA B149.1, Natural Gas and Propane Installation
Code.
See the Rinnai Boiler Applications Manual for further information on venting.