11.0 Commissioning
11.5
Starting the Appliance and Checking the Gas
Rate (cont)
10. Carry out the rate measurement. The burners will remain
at maximum rate unless: -
a) A fault condition occurs – the burner/s will switch off
– depending on the fault.
b) The boiler set flow condition is reached (see note) –
the burners will switch off.
c) The power generated reaches 1kW - the engine
burner will modulate down.
For this reason the measurement needs to be carried out on
a cold system to be sure of obtaining an accurate result.
NOTE: The boiler set flow temperature is set to 90° to
avoid interruption of the rate measurement.
11. The chimney sweep function can be deactivated in the
same manner as it is activated. It will deactivate automatically
after 20 minutes, or in the event of an fault.
12. Remember: The engine burner will not restart until the
Head Temperature is below 165°C.

12.0 Completion

12.1
Completion
1. Instruct the user in the operation of the boiler and system
including the THINK Controller, explaining the operational
sequence.
2. Set the central heating and hot water temperature comfort
levels to the requirements of the user.
3. Carefully read and complete all sections of the Benchmark
Commissioning Checklist at the rear of this publication that
are relevant to the appliance and installation. These details
may be required in the event of any warranty work. The
publication must be handed to the user for safe keeping and
each subsequent regular service visit recorded.
4. Complete the 'Notice of Installation' booklet and submit on
the day of commissioning to the Distribution Network
Operator.
5. For IE, it is necessary to complete a "Declaration of
Conformity" to indicate compliance with I.S. 813. An example
of this is given in I.S. 813 "Domestic Gas Installations". This is
in addition to the Benchmark Commissioning Checklist.
6. Hand over the Users Operating, Installation and Servicing
Instructions giving advice on the necessity of regular servicing.
Advise the customer of the necessity of informing the
electricity provider with regard to billing and payback. See
the Users Operating instructions section 13.3.
NOTE: See also