Unpack The Premium 50 Kva Ups (With Casters) - Toshiba 4200FA Installation And Operation Manual

Three-phase 15/25/30/50 kva ups
Hide thumbs Also See for 4200FA:
Table of Contents

Advertisement

2.3

Unpack the Premium 50 kVA UPS (with Casters)

(EXCLUDING Seismic and Base models – See 2.4)
Carefully inspect the UPS for shipping damage. Units
wrapped; those outside North America are crated.
3. Place the tie brackets in the slots at
the lower end of the ramps.
SLOWLY roll the unit down the
ramp.
4. Save the loading rails for
seismic anchoring of the UPS.
See pg. 15.
DANGER
12
1.
Remove shrink wrap material.
TOP HEAVY EQUIPMENT. IMPROPER LIFTING CAN RESULT IN INJURY OR DEATH.
LIFT AND MOVE CAREFULLY AND ONLY WITH ADEQUATE EQUIPMENT AND TRAINED
PERSONNEL. THIS EQUIPMENT WILL TIP OVER EASILY UNTIL FIXED IN PLACE.
4200FA Installation and Operation Manual
shipped within North America are shrink-
2. Unbolt the rails from both the unit
and the shipping pallet.
Place the rails on the front of
the pallet.
Use the four 1/2 x 3" bolts to
secure the rails to the shipping
pallet.
Attach the rails as shown in the
front to the front of the pallet.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

4200fa ct

Table of Contents