Implementing A Power Plan - 3Com 3C17205-US - Corp SUPERSTACK 3 SWITCH 4400 24PORT Implementation Manual

Implementation guide
Table of Contents

Advertisement

2 Any device connected to a lower port number will take priority over a
Implementing a
Power Plan
have not had their power guaranteed. See
Power Plan"
on
page
device connected to a higher port number.
If the Switch needs to remove power from a device it will remove power
from the highest numbered port that has not been guaranteed power.
Devices that have been guaranteed power are not affected.
When the Switch is power cycled it will supply power first to guaranteed
ports that request power, then to the remaining ports, starting at the
lowest numbered port first.
If the total power required by your Power over Ethernet devices is less
than the Switch's power budget then you can guarantee power to every
port.
If the total power required by your Power over Ethernet devices is more
than the Switch's power budget then you will not be able to guarantee
power to all devices. If this is the case you may choose to:
Add additional Power over Ethernet switches — This will enable to
you guarantee power to each port on the Switch that supplies a
Power over Ethernet device. The remaining ports can be used to
supply networking to those devices that are powered by other means.
Prioritize Power over Ethernet devices — Since the Switch supplies
power to the lowest numbered port first, you should connect your
Power over Ethernet devices in order of importance, the most
important device being connected to the lowest numbered port. By
monitoring power consumption and checking if any devices have
been refused power you can decide whether additional Power over
Ethernet Switches will be required.
Guarantee power to critical devices — If you add an important Power
over Ethernet device to a high numbered port, you can still guarantee
power to this port (see
below). The following rules apply to guaranteed power:
If you guarantee power to all active ports then no ports will be
disconnected or refused power. When additional Power over
Ethernet devices are added to your Switch, they will only be
116.
"Configuring a Guaranteed Power Plan"
Planning Power Budgets
"Configuring a Guaranteed
115

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

3c172033c172043c172053c172064400

Table of Contents