E. CHECKOUT and STARTUP
The Checkout and Startup procedure prepares a recently installed or repaired COMBI for
operation. The procedures check proper electrical, gas, water, and drain connections to the
COMBI, and verify basic COMBI operation.
TASK
Preparation
Check operating location clearances
Test supply water quality
Verify Electric Power Requirements.
Verify Gas Supply Requirements
Verify Exhaust Hood Requirements
Installation
Check Exhaust Hood
Check electrical line connection
Check water supply connection
Leak Test water supply lines
Check Gas Supply Connection
Leak Test Gas Supply Connection
Verify Combi is level
Check drain line connection
Perform Burner Ignition Test
Perform Startup Test
Notes:
Table 2-5 Installation Check List
REFERENCE
Page No.
22
COMPLETED
9
11
10
16
18
18
10
11
11
16
16
20
14
23
23

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents