Completing the installation
To complete the installation, complete the following tasks. Instructions for each task
are in the following sections.
1. Reinstall the blade server bezel assembly, if you removed it (see "Installing the
2. Close the blade server cover (see "Closing the blade server cover").
3. Reinstall the blade server into the BladeCenter unit (see "Installing the blade
4. Turn on the blade server (see "Turning on the blade server" on page 11).
5. For certain options, run the blade server Configuration/Setup Utility program
Installing the blade server bezel assembly
See the illustration in "Removing the blade server bezel assembly" on page 18 for
information about installing the bezel assembly.
To install the blade server bezel assembly, complete the following steps:
1. Read the safety information beginning on page v and "Installation guidelines" on
2. Connect the control-panel cable to the control-panel connector on the system
3. Carefully slide the bezel assembly onto the blade server until it clicks into place.
Closing the blade server cover
Important: The blade server cannot be inserted into the BladeCenter unit until the
cover is installed and closed. Do not attempt to override this protection.
The following illustration shows how to close the blade server cover.
blade server bezel assembly" for information on installing the bezel assembly).
Statement 21:
CAUTION:
Hazardous energy is present when the blade server is connected to the
power source. Always replace the blade cover before installing the blade
server.
server in a BladeCenter unit" on page 30).
(see "Updating the blade server configuration" on page 32).
Note: If you have just connected the power cords of the BladeCenter unit to
electrical outlets, you must wait until the power-on LED on the blade
server flashes slowly before pressing the power-control button.
page 15.
board.
Chapter 3. Installing options
29