Figure 4-14. Attaching a cable management arm bracket to the server

Loading the Rack Server

Load and secure the server to the rack with the face plate thumb screws before
continuing to attach any more mounting bracket assemblies. Ensure that this
pair of brackets is perfectly aligned and installed and that the server fits before
you continue.
!
IMPORTANT: To make the server lighter and more manageable, do not install
drives in the server until after you load the server into the rack.
WARNING: To avoid the risk of personal injury or damage to the
equipment, a minimum of two people MUST lift the server into the rack.
The server weighs 50 pounds (22.6 kilograms). If the unit is to be loaded
above chest level, a third person must assist in aligning the rails while the
other two support the unit.
CZR4-014.EPS