Rack-Mountable Server Installation

Loading the Rack Server

Load and secure the server to the rack with the face plate thumbscrews before
continuing to attach any more mounting bracket assemblies. Make sure that this
pair of brackets is correctly aligned and installed and that the server fits before
you continue.
IMPORTANT: To make the server lighter and more manageable, do not
install drives in the server until after you load the server into the rack. You
may also temporarily remove power supplies and reinstall them after you
have mounted the server in the rack.
For use with 350-MHz or greater Intel processor-based servers only
Writer: Cheri Stewart Project: Compaq ProLiant 3000 Servers Setup and Installation Guide Comments: 179776-002
WARNING: To reduce the risk of personal injury or damage to
the equipment, a minimum of two people MUST lift the server
into the rack. The server weighs 50 pounds (22.6 kilograms). If
the unit is to be loaded above chest level, a third person must
assist in aligning the rails while the other two support the unit.
File Name: D-CH03.DOC Last Saved On: 1/12/99 1:24 PM
COMPAQ CONFIDENTIAL - NEED TO KNOW REQUIRED