11. Pipe insulation

After finishing the leak test and vacuum drying, the
piping must be insulated. Take into account the following
points:
Make sure to insulate the connection piping and
refrigerant branch kits entirely.
Be sure to insulate the liquid piping and gas piping
(for all units).
Use heat resistant polyethylene foam which can
withstand a temperature of 70°C for liquid piping and
polyethylene foam which can withstand a
temperature of 120ºC for gas piping (for all units).
Reinforce the insulation on the refrigerant piping
according to the installation environment.
Ambient
temperature
≤30°C
75% to 80% RH
>30°C
If there is a possibility that condensation on the stop
valve might drip down into the indoor unit through
gaps in the insulation and piping because the outdoor
unit is located higher than the indoor unit, this must
be prevented by sealing up the connections.
See below figure.
2
1
5

12. Electrical wiring work

12.1 Precautions on electrical wiring work

WARNING
Electrical installation. All field wiring and
components must be installed by a licensed
electrician and must comply with the applicable
legislation.
NOTICE
Electrical wiring work recommendations.
To persons in-charge of electrical wiring work:
Do not operate the unit until the refrigerant
piping is complete. "10.4 Leak test and vacuum
drying". Running the unit before the piping is
ready will break the compressor.
DANGER: ELECTRICAL SHOCK
See "2. General safety precautions".
01_EN_3P748230-1.indd 31
Humidity
Minimum thickness
15 mm
≥80% RH
20 mm
1 Insulation material
4
2 Caulking, etc.
3
3 Liquid pipe stop valve
4 Gas pipe stop valve
5 Connection pipe
1
WARNING
A main switch or other means for disconnection,
having a contact separation in all poles, must be
incorporated in the fixed wiring in accordance
with the applicable legislation.
Use only copper wires.
All field wiring must be carried out in
accordance with the wiring diagram supplied
with the unit and the instructions given below.
Never squeeze bundled cables and be sure
that it does not come in contact with the
non-insulated piping and sharp edges.
Be sure no external pressure is applied to the
terminal connections.
Power supply wires must be attached securely.
If the power supply has a missing or wrong
N-phase, equipment will break down.
Be sure to establish an earth. Do not earth
the unit to a utility pipe, surge absorber,
or telephone earth.
Incomplete earth may cause electrical shock.
Be sure to install an earth leakage protector.
Failure to do so may cause electric shock or
fire.
Be sure to use a dedicated power circuit,
never use a power supply shared by another
appliance.
When installing the earth leakage protector
be sure that it is compatible with the inverter
(resistant to high frequency electric noise) to
avoid unnecessary opening of the earth
leakage protector.
As this unit is equipped with an inverter,
installing a phase advancing capacitor not
only will deteriorate power factor improvement
effect, but also may cause a capacitor
abnormal heating accident due to high
frequency waves.
Therefore, never install a phase advancing
capacitor.
Since this product is equipped with an
inverter, harmonics will be generated.
If local laws require the suppression of
harmonics on the building, please take
harmonic suppression measures on the
electrical equipment side.
Be sure to install the required fuses or circuit
breakers.
Do not operate until refrigerant piping work is
completed.
(If operated before completion of the piping
work, the compressor may break down.)
Never remove a thermistor, sensor, etc., when
connecting power wiring and transmission
wiring.
(If operated without thermistor, sensor, etc.,
the compressor may break down.)