Installation Checklist - Eaton 93E15KMBSB User And Installation Manual

Small and large external battery cabinet
Table of Contents

Advertisement

6 Installation checklist

All packing materials and restraints have been removed from each cabinet.
Each cabinet in the UPS system is placed in its installation location.
A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.
All conduits and cables are properly routed to the UPS and any ancillary cabinets.
All power cables are properly sized and terminated.
Neutral conductors are installed as per requirements.
A ground conductor is properly installed.
Battery cables are terminated and connected to battery connectors.
Battery Shunt trip and Aux contact signal wiring is connected from the UPS to the battery
cabinet. Note: 93PM only!
Room ventilation and air conditioning equipment are installed and operating correctly.
The area around the installed UPS system is clean and dust-free. (It is recommended that the
UPS be installed on a level floor suitable for computer or electronic equipment.)
Adequate workspace exists around the UPS and other cabinets.
Adequate lighting is provided around all UPS equipment.
A 230 VAC service outlet is located within 7.5 meters of the UPS equipment.
Alarm relays and signal inputs are wired appropriately. (OPTIONAL)
A remote battery disconnect control is mounted in its installation location and its wiring is
terminated inside the UPS and battery cabinet. (OPTIONAL)
Accessories are mounted in installation locations and wiring is terminated inside the UPS
cabinet. (OPTIONAL)
Startup and operational checks are performed by an authorized Eaton Customer Service
Engineer
P-164000427
Revision 2
SMALL and LARGE BATTERY CABINET
User's and Installation Guide
20

Advertisement

Table of Contents
loading

This manual is also suitable for:

93e93p

Table of Contents