Cable connection to battery poles is to be done as follows:
Figure 2 -5: Cable connection on b attery poles
9. If multiple cabinets are to be used, repeat the steps for the rest of the cabinets and
in 93PM system be sure to daisy chain the signal wire harnesses in the next
cabinet. 93E system does not use signal wiring. Signal wires are daisy chained
by cutting the multiple connector and extra length of the cables and connecting them to
TB2 terminals 5-8. Look at the Figure 2-6.
Figure 2 -6: Signal wiring of Large and Small Battery Cabinet .
P-164000427
Revision 2
SMALL and LARGE BATTERY CABINET
User's and Installation Guide
12