Alternate Moving Method

6. If it is not possible to rig from above as shown in the figures, the unit may also be moved by

Isolation Pads

The elastomeric pads shipped (as standard) are adequate for most installations. For additional
details on isolation practices, refer to Trane Engineering Bulletin -Series R® Chiller Sound Rat-
ings and Installation Guide., or consult an acoustical engineer for sound-sensitive installations.
7. During final positioning of the unit, place the isolation pads under the evaporator and con-

Placement Neoprene Isolator Installation (optional)

8. Install the optional neoprene isolators at each mounting location.
40
jacking each end high enough to move an equipment dolly under each tube sheet support.
Once securely mounted on the dollies, the unit may be rolled into position.
denser tube sheet supports. Level the unit .
8.1 Secure the isolators to the mounting surface, using the mounting slots in the isolator
base plate, as shown as below. Do not fully tighten the isolator mounting bolts at this
time.
8.2 Align the mounting holes in the base of the unit, with the threaded positioning pins on
the top of the isolators.
8.3 Lower the unit on to the isolators and secure the isolator to the unit with a nut. Maxi-
mum isolator deflection should be approximately 1/4".
8.4 Level the unit carefully. Refer to "Leveling". Fully tighten the isolator mounting bolts.
8.5 Two Isolators for each foot, refer to
Figure
12, total 8 isolators installed for one chiller.