Rigging, Lifting, And Moving The Chiller - Trane Arctic Manhattan Gen II Installation, Operation And Maintenance Manual

Air-cooled modular chiller
Table of Contents

Advertisement

Rigging, Lifting, and Moving the
Chiller
The Manhattan™ Gen IIAir-Cooled Modular Chiller can
be delivered to the customer's site as individual
modules or as previously assembled single units,
depending on customer requirements and preferences.
Limitations on the methods and materials that can be
used to rig, lift, or move a chiller or an individual
module include:
Maintain the module in an upright position at all
times.
Certain configurations of modules can be top-
heavy. Move modules slowly with consideration for
each module's center-of-gravity.
Figure 3. Recommended chiller rigging assembled unit
ARTC-SVX001B-EN
Rig, lift, and move by strapping and lifting using a
properly configured floor jack or fork lift or by
overhead means.
Position lifting beams to prevent lifting straps from
rubbing or contacting module side panels or
electrical boxes.
Do not use cables, chains, or any other type of
metalized strapping to lift a module.
Do not push a chiller module while directly in
contact with the floor using manual or mechanical
means.
I I n n s s t t a a l l l l a a t t i i o o n n M M e e c c h h a a n n i i c c a a l l
17

Advertisement

Table of Contents
loading

This manual is also suitable for:

Arctic thermafit manhattan amc series

Table of Contents