Y: CHECKOUT PROCEDURES:
The final phase of the installation is the system Checkout Procedures. The following list represents the most
common items covered in a Checkout Procedure. Confirm all requirements in this document have been met.
All wiring connections are tight and properly
secured.
Voltage and running current are within limits.
All refrigerant lines (internal and external to
equipment) are isolated, secure, and not in direct
contact with each other or structure.
All braze connections have been checked for leaks.
A vacuum of 350 microns provides confirmation
that the refrigeration system is leak free and dry.
Additional refrigerant weight is recorded on a label
by the unit nameplate.
If unit is installed in any orientation other than
upflow, refrigerent sensor is properly relocated.
Final unit inspection to confirm factory tubing
has not shifted during shipment. Adjust tubing if
necessary so tubes do not rub against each other
or any component when unit runs.
Ductwork is sealed and insulated.
22
All drain lines are clear with joints properly sealed.
Pour water into drain pan to confirm proper
drainage. Provide enough water to ensure drain
trap is primed.
Supply registers and return grilles are open,
unobstructed, and air filter is installed.
Indoor blower and outdoor fan are operating
smoothly and without obstruction.
Indoor blower motor set on correct speed setting to
deliver required CFM. "Blower and fan set screws
are tight."
Cover panels are in place and properly tightened.
System functions safely and properly in all modes.
Refrigerent leak detection system mitigation actions
are verified.
All refrigerent safety procedures have been verified.
Owner has been instructed on use of system and
given manual.
18-AD47D1-1B-EN