Panel Preparation - Close Mount (Kit 2 - 4 Conduit) - Trane RTHD Installation Instructions Manual

Afdr retrofit air-cooled adaptive frequency drive
Hide thumbs Also See for RTHD:
Table of Contents

Advertisement

Installation
Figure 36. Conduit hole locations
1
Note: See
"Dimensions," p. 9
dimensions.
Panel Preparation – Close Mount
(Kit 2 – 4 conduit)
Refer to
Figure 37
during the following procedure.
2. Drill four 2.5-inch diameter holes at Locations 1– 4, as
shown in
Figure
37. These holes will be used to route the
power wire which connects the unit to the AFD.
Figure 37. Power conduit hole locations
1
2
36
2X Holes Drilled
2X Ø 2.5
Panel Bottom
2
for conduit location
2-4X Holes Drilled
2-4X Ø 2.5
Panel Bottom
4
3
Panel Front
Notes:
Test-fit the 2.5-inch conduit fittings at the locations to
ensure the conduit and or fitting will not interfere with the
unit evaporator and or panel before drilling holes.
Depending on the unit's evaporator size the holes may be
located further inward than specified without interference
between conduit and evaporator. Locating the holes
further inward will aid in harness installation later. Before
drilling, make sure conduit and fittings will not interfere with
evaporator or panel door.
Panel Front
SO-SVN048A-EN