Piping
Check boiler and system piping for any sign of leakage; make sure
Near boiler piping
pipes are properly supported.
Check condition of all vent pipes and joints. Ensure the vent piping
Vent
terminations are free of obstructions and blockages.
System
Visual
Do a full visual inspection of all system components.
Functional
Test all functions of the system (Heat, Safeties).
Verify safe settings on boiler or anti-scald valve.
Temperatures
Verify programmed temperature settings.
Electrical
Connections
Check wire connections. Make sure connections are tight.
Smoke and CO
Verify devices are installed and working properly. Change batteries if
Detector
necessary.
Circuit Breakers
Check to see that the circuit breaker is clearly labeled. Exercise circuit
breaker.
Switch and Plug
Verify ON/OFF switch and convenience plug are both functional.
Chamber / Burner
Check burner tube and combustion chamber coils. Clean according
Combustion
to maintenance section of manual. Vacuum combustion chamber.
Chamber
Replace any gaskets that show signs of damage.
Spark Electrode
Clean. Set gap at 1/4" Clean probe with plumbers cloth to remove
oxides.
Combination Ignitor
Check ionization in uA (d7 in Status Menu in Start-Up Procedures).
and Flame Probe
Record high fire and low fire. Clean probe with plumbers cloth to
remove oxides.
Condensate
Neutralizer
Clean out condensate neutralizer. Use wet/dry vacuum. Check for all
potential obstruction issues. Replenish marble chips or lime crystals if
needed (no smaller than ¾"). Refill system with water. WARNING: You
must verify flow of condensate and make sure the cap is connected
properly before leaving boiler unattended.
Condensate System
Check entire condensate system to make sure there are no
obstructions in flow. Make sure the condensate pump is working
properly, verify all connections.
Gas
Pressure
Measure incoming gas pressure (3.5 to 14" WC).
Pressure Drop
Measure drop in pressure on light off (no more than 1" WC).
Check Gas Pipe for
Check gas piping. Test for leaks and signs of aging. Make sure all pipes
Leaks
are properly supported.
Combustion
CO / CO2 Levels
Check CO and CO2 levels in exhaust. See Start-Up Procedures for
ranges. Record at high and low fire.
Safeties
ECO (Energy Cut
Check continuity on flue and water ECO. Replace if corroded.
Out)
Sensors
Check wiring. Verify through ohms reading.
Final Inspection
Check List
Verify that you have completed entire check list. WARNING: FAILURE
TO DO SO COULD RESULT IN SERIOUS INJURY OR DEATH.
Homeowner
Review what you have done with the homeowner.
Table 30 - *Continue annual maintenance beyond the 4th year as required.
Inspection Activities
Date Last Completed
rd
1st Year 2nd Year 3
Year 4th Year*
rd
1st Year 2nd Year 3
Year 4th Year*
rd
1st Year 2nd Year 3
Year 4th Year*
rd
1st Year 2nd Year 3
Year 4th Year*
rd
1st Year 2nd Year 3
Year 4th Year*
3rd
1st Year 2nd Year
Year
rd
1st Year 2nd Year 3
Year 4th Year*
rd
1st Year 2nd Year 3
Year 4th Year*
whl-428-r1 Rev. 001 Rel. 012 Date 7.21.20
57
4th Year*

Advertisement

Table of Contents
loading

This manual is also suitable for:

Premium wbcmc 1700 series

Table of Contents