Final Instructions; Handover - Baxi 800 Combi 2 Series Installation And Service Manual

High-efficiency wall-hung condensing gas boiler
Hide thumbs Also See for 800 Combi 2 Series:
Table of Contents

Advertisement

7.5

Final instructions

Fig.53
People
52
800 Combi 2
7.5.1

Handover

1. Carefully read and complete all sections of the Benchmark Commis­
sioning Checklist at the rear of this publication that are relevant to
the boiler and installation. These details will be required in the event
of any warranty work.
Important
The warranty will be invalidated if the Benchmark section is in­
complete.
2. The publication must be handed to the user for safe keeping and
each subsequent regular service visit recorded.
3. Hand over the User Quick Start Guide, Installation and Servicing
Manual, giving advice on the necessity of regular servicing.
4. For IE, it is necessary to complete a "Declaration of Conformity" to
indicate compliance with I.S. 813. An example of this is given in I.S.
813 "Domestic Gas Installations" . This is in addition to the Bench-
mark Commissioning Checklist.
5. Set the central heating and hot water temperatures to the require-
ments of the user. Instruct the user in the operation of the boiler and
system.
6. Instruct the user in the operation of the boiler controls.
7. Demonstrate to the user the action required if a gas leak occurs or is
suspected. Show them how to turn off the gas supply at the meter
control, and advise them not to operate electric light or power
switched, and to ventilate the property.
8. Show the user the location of the system control isolation switch, and
demonstrate its operation.
9. Advise the user that they may observe a plume of vapour from the
flue terminal, and that it is part of the normal operation of the boiler.
7 Commissioning

Advertisement

Table of Contents
loading

This manual is also suitable for:

824 combi 2830 combi 2836 combi 2

Table of Contents