Adjustment Of Synchronizer - Pfaff performance 2054 Service Manual

Service manual
Hide thumbs Also See for performance 2054:
Table of Contents

Advertisement

5. Adjustment of synchronizer

Note:
The following machine positions or functions are controlled by the synchronizer:
1. Change of feeding direction and change of stitch length
2. Sideways movement of needle bar
3. Take-up lever top position/needle „up" position
4. Needle „down" position
This adjustment must only be carried out when compelling reasons exist!
It must be performed with absolute accuracy.
Requirement:
A change of sideways needle bar movement must take place when the needle in its upward movement is
7 mm above the needle plate surface (fig. 13).
When the machine stops with the take-up lever in top position, the take-up lever must have nearly reached
the upper dead center.
Check:
Insert a new needle.
Remove the presser foot.
Turn on the master switch.
Select stitch pattern „3" with stitch width „9" and stitch length „2".
Turn the handwheel forward by one full turn.
Continue turning the handwheel slowly and check the timing of the needle bar
sideways movement.
Adjustment:
Remove the folding cover and the housing insert.
Loosen fastening screw 34 of cam 35 just slightly (fig. 14).
Turn the handwheel a full rotation forwards, then keep on turning it until the needle is
about 7 mm above the needle plate surface (fig. 15).
Keep on turning cam 35 very slowly until the zigzag stepping motor switches (fig. 14).
Tighten fastening screw of cam 34.
Make sure that the lobes of cam 36 rest in the center of the circuit board guides.
Cross-Check:
Turn the handwheel slowly and check the timing of the needle bar sideways
movement.
A change of feed direction or stitch length must take place when the feed dog has
sunk 0.3+/-0.02 mm below the needle plate surface.