Installation

FRESH AIR HOOD INSTALLATION

Fresh air hood assembly steps
Horizontal flow
FWD
Power supply
Capacities
Cooling capacity on water (1)
Heating capacity on water (2)
Fan motor
Fan power input (3)
Current amps (3)
Start-up amps
Air flow
minimum
nominal
maximum
Main coil
Water entering/leaving connections
Step 1: Remove sheet
Electric heater (accessory for blower only)
Electric power supply
metal hood set.
Heating capacity
Hot water coil (accessory for blower only)
Heating capacity (4)
G2 filter (filter box accessory)
Quantity
Dimensions ( LxWxth)
G4 filter (filter box accessory)
Quantity
Dimensions ( LxWxth)
Condensate pump (accessory)
Water flow - lift height
Not available for FWD30 and FWD45
Sound level (L/M/H speed)
Sound pressure level (5)
Sound power level (5)
Step 4: Repeat the steps 2 and 3
Unit dimensions
Width x Depth
for the second hood
Height
Shipped unit dimensions
Width x Depth
Down flow
Height
Weight
Colour
Recommended fuse size
Unit alone (aM/gI)
Unit with electric heater (gI)
(1) Conditions: Water entering/leaving temperature: 7/12 °C, Air inlet temperature 27/19°C DB/WB - Nominal air flow
(2) Conditions: Water entering/leaving temperature: 50/45 °C, Air inlet temperature 20°C DB - Nominal air flow
(3) At high speed with nominal air flow.
(4) Water entering/leaving temperature 90/70 °C, air inlet temperature 20 °C DB, Nominal air flow.
(5) A rectangular glass wool duct 1m50 long is placed on the blower.The measurement is taken in the room containing the blower unit.
Heat exchanger operating limits:
FWD:
*water temperature: max 100° C
*absolute service pressure: min 1 bar/max 11 bars
Step 1: Remove sheet
Accessories - Hot water coil:
*water temperature: min. +2° C/max. 100° C
metal hood set.
*absolute service pressure: min 1 bar/max 11 bars
4
30
Technical Data
08
(V/Ph/Hz)
(kW)
5,2
(kW)
6,3
(type)
(kW)
0,23
(A)
1,1
(A)
3,2
(m
/h)
490
3
(m
/h)
820
3
(m
/h)
980
3
(type)
(Dia)
3/4"
Step 2: Position side flange
(V/Ph/Hz)
230/1/50
with corner on the outside
(kW)
2/4
(kW)
6,3
2
(mm)
386x221x8
-
(mm)
-
(type)
(l/h - mm)
(dB(A))
36/40/43
(dB(A))
46/50/53
Step 5: Repeat the steps 2 and 3 for the third hood
(mm)
890 x 600
(mm)
250
(mm)
933 x 644
(mm)
260
(kg)
32
(A)
8/16
(A)
16 (2kW),25 (4kW)
Step 2: Position side flange
with corner on the outside
12
20
230/1/50
8,3
15
11,9
18,9
2 x direct drive centrifugal
0,46
0,65
2,2
3,1
5,5
9,3
980
1400
1650
2300
1970
2600
ISO R7 rotating female
3/4"
1 1/2"
Step 3: position the cover hood
230/1/50 or 400/3/50
400/3/50
8
10
12
17,4
2
2
486x271x8
586x321x8
2
2
486x264x48
586x314x48
Centrifugal
24 - 500
38/41/44
46/50/53
48/51/54
56/60/63
1090 x 710
1290 x 820
300
350
1133 x 754
1333 x 864
310
360
46
61
galvanised steel
8/16
8/16
40 (230V),3*16 (400V)
3*20
Step 3: position the cover hood
30
45
18,8
30,1
20,9
38,2
1,04
1,51
4,7
5,5
14,1
16,5
1800
2700
3000
4500
3600
5400
1 1/2"
1 1/2"
400/3/50
400/3/50
12
12
22,4
34,5
2
2
586*421*8
586*621*8
2
2
586*414*48
586*614*48
47/52/57
47/52/58
57/62/67
57/62/68
1290 x 970
1290 x 1090
450
650
1333 x 1008
1333*1133
460
660
76
118
8/25
8/25
3*25
3*25
UNT-PRC002-GB
RT-SVX060A-GB

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Airfinity xl ic

Table of Contents