Trane GAF2A0A36S3AEC Installer's Manual page 28

50 hz convertible air handlers 3 – 5 ton
Table of Contents

Advertisement

STEP 4 - Install a clean-out tee in the primary
drain line for future maintenance. It is recom-
mended that you install a cap on the top of the
tee.
STEP 5 - Insulate the primary drain line to
prevent sweating where dew point temperatures
may be met. (Optional depending on climate
and application needs.)
Provide a means of drainage to prevent winter
freeze-up of condensate line. (Optional depend-
ing on climate and application needs.)
STEP 6 - Support the condensate piping outside
the unit per local codes for proper drainage and
to prevent sagging.
Allow 1/4" of downward slope for each foot of
pipe.
28
1.5" minimum
clearance is
recommended
from cabinet to
inside edge of
tubing
CONDENSATE
PIPING
SUPPORTS
HEATER
HEATER
1.5" min.
COIL
BLOWER/FILTER
COIL
BLOWER/FILTER
Cap
Tee
Insulation