Commissioning, Inspec-Steps - Commissioning, Inspection And Maintenance - Viessmann Vitocrossal 300 Service Instructions Manual

Hide thumbs Also See for Vitocrossal 300:
Table of Contents

Advertisement

Commissioning, inspection, maintenance
Steps - commissioning, inspection and maintenance
Commissioning steps
Inspection steps
Maintenance steps
1. Information on maintenance work....................................................................................
2. Checking the high limit safety cut-out setting................................................................
3. Filling the heating system with water and venting.........................................................
4. Filling the trap with water..................................................................................................
5. Commissioning the system...............................................................................................
6. Checking the gas type....................................................................................................... 10
7. Converting to natural gas LL............................................................................................ 10
8. Checking static pressure and supply pressure.............................................................. 11
10. Checking the CO content
12. Checking the ionisation current....................................................................................... 14
13. Shutting down the system................................................................................................. 14
14. Opening the boiler door..................................................................................................... 15
16. Cleaning the combustion chamber and heating surfaces............................................. 17
17. Checking the gaskets and thermal insulation sections................................................. 17
19. Cleaning and reconnecting the condensate drain system............................................. 17
21. Checking the burner gauze assembly.............................................................................. 18
22. Checking the ignition and ionisation electrodes............................................................ 19
23. Cleaning the burner........................................................................................................... 19
24. Installing the burner........................................................................................................... 20
25. Closing the boiler door...................................................................................................... 20
26. Automatic tightness test on the two gas train valves.................................................... 20
27. Checking the filter element in the gas line (if installed) and replacing if required
28. Checking all gas connections for tightness.................................................................... 21
29. Checking the rotary damper setting................................................................................. 21
30. Performing final checks..................................................................................................... 22
31. Checking the water quality................................................................................................ 22
used (DCC system)............................................................................................................ 22
34. Checking the expansion vessel and system pressure................................................... 22
35. Checking the flue gas collector for tightness................................................................. 23
36. Checking the mixer for ease of operation and leaks...................................................... 23
6
content................................................................................................. 12
2
Page
8
8
8
8
9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ct3u

Table of Contents