2
Installing the AP
Installation flowchart
Figure2-1 Installation flowchart
On a wall
Pre-installation tasks
Before installing the AP, perform the following tasks:
•
Connect the AP to a power source and the network. Examine the LEDs to verify that the AP is
operating correctly. For information about AP LEDs, see "LEDs."
•
Record the MAC address and serial number at the rear of the AP for future use.
•
Make sure you have completed cabling at the installation site.
•
To ensure the transmission rate, use a CAT6 or above cable to connect the 10GE port.
Start
Complete pre-installation
tasks
Determine the installation
position
Mount the AP
Connect the AP to the
power source
Connect the AP to the
network
End
On a ceiling
2-1