Operation
8.8 Re-commissioning the machine
Type of construction IM B3
Use the coolant drain hole
①
②
Other types of construction
In other types of construction, you must blow the coolant out with compressed air.
8.8
Re-commissioning the machine
When you re-commission the machine, proceed as follows:
● Study the record made when the machine was decommissioned, and reverse the measures
● Perform the measures listed in the "Commissioning" section.
See also
Start-up (Page 97)
8.9
Switching on again after an emergency switching-off
● Check the machine before recommissioning the driven machine after an Emergency Off.
● Eliminate all the causes that have led to the emergency off
116
Coolant connection
Coolant connection and coolant drain hole
that were taken for conservation and storage.
②
in the bearing shield to drain the coolant.
SIMOTICS FD 1LH1
Operating Instructions 01/2019