Figure 39 Cabinet stack up for R840 servers
40
Empty
39
38
R840
37
R840
36
35
34
R840
33
32
R840
31
30
R840
29
28
R840
27
26
R840
25
Data Switch
24
Data Switch
23
Empty
22
Management Switch
21
Management Server
20
19
R840
18
17
R840
16
15
R840
14
13
R840
12
11
R840
10
9
R840
8
7
R840
6
5
R840
4
3
2
Empty
1

Installation of the equipment in the cabinet

Install equipment in the cabinet or rack. Always begin component installation at the bottom of the cabinet and work
upward. Install components at the lowest available space for that component type.
Placement of the equipment in the cabinet is dependent on the type of power distribution units installed in the cabinet.
Refer to the equipment stack up guidelines for each type of power distribution.
Install the servers as described in the following sections. Most of the servers will function as VxFlex Ready
l
Node nodes, and at least one will function as a management server. The procedures for physical installation in
the rack or cabinet apply to both types. Once the servers have been installed, refer to the VxFlex Ready Node
Hardware Configuration and Operating System Installation Guide (for your system's operating system), for server
configuration and operating system installation procedures.
Dell EMC VxFlex Ready Node Server Installation Guide
R840 Equipment Installation
83

Advertisement

Table of Contents
loading

This manual is also suitable for:

Emc vxflex ready node r640Emc vxflex ready node r740xd

Table of Contents