1U1N Configuration Equipment Installation

Installation of the equipment in the cabinet

Installation in cabinets with single-phase power distribution

Hardware Installation Guide
18
Always begin component installation at the bottom of the cabinet and work upward.
Install components at the lowest available space for that component type.
Placement of the equipment in the cabinet is dependent on the type of power
distribution units installed in the cabinet. Refer to the equipment stack up guidelines
for each type of power distribution.
Install the RX630 servers as described in the following chapters. Most of the
l
servers will function as VxFlex Ready Node nodes, and at least one will function as
a management server. The procedures for physical installation in the rack or
cabinet apply to both types. Once the servers have been installed, refer to the
VxFlex Ready Node Series Hardware Configuration and Operating System Installation
Guide for server configuration and operating system installation procedures.
Install the management switches
l
Install the data switches
l
Note
Install all the equipment in the cabinet before installing and connecting the power and
I/O cables.
Install the equipment as described in
l
page 18.
If you are installing the minimum configuration, refer to the figure and table below
l
for minimum configurations for the equipment stack up in the cabinet.
If you are installing the maximum configuration, refer to the figure and table below
l
for maximum configurations for the equipment stack up in the cabinet.
Component
Description
Function
Data Server
RX630 Server
Management Server
Management Server
Management Switch
Customer provided 1
GbE switch
Data Switch
Customer provided 10
GbE switch

Installation of the equipment in the cabinet

Table 3 Minimum configuration in single-phase power
distribution cabinets
Quantity
3
1
1
2
on
Cabinet U Space
2 - 4
18
19
21 - 22