4 Set-up
The product's installation depth B can be found in the tech-
nical data in the appendix.
4.4
Minimum clearances
C
C
A
165 mm: Air/flue pipe, 60/100 mm diameter
275 mm: Air/flue pipe, 80/125 mm diameter
B
180 mm; optimum approx. 250 mm
C
5 mm; optimum approx. 50 mm
D
500 mm in front of the heat generator to enable
easy access for maintenance work (may be
provided by an opening door).
4.5
Using the installation template
▶
Use the installation template to ascertain the locations at
which you need to drill holes and make perforations.
8
D
Minimum clearance
4.6
Wall-mounting the product
1.
Check whether the wall has sufficient load-bearing ca-
pacity to bear the operational weight of the product.
2.
Check if the supplied fixing material may be used for
the wall.
Conditions: The load-bearing capacity of the wall is sufficient, The fixing
material may be used for the wall
▶
Wall-mount the product as described.
Conditions: The load-bearing capacity of the wall is not sufficient
▶
Ensure that wall-mounting apparatus on-site has a suf-
ficient load-bearing capacity. Use individual stands or
primary walling, for example.
▶
Do not wall-mount the product if you cannot provide
wall-mounting apparatus with a sufficient load-bearing
capacity.
Conditions: The fixing material may not be used for the wall
▶
Wall-mount the product as described in the illustration
using the permitted fixing material provided on-site.
Installation and maintenance instructions ecoTEC exclusive 0020189875_01