Removal and Installation

REMOVE PULLEY SUPPORTS AND/OR PULLEY ONE BY ONE.
ALWAYS REPLACE AND SECURE A PULLEY SUPPORT AND/OR
A PULLEY BEFORE REMOVING ANOTHER ONE. THE SAME SUIT-
ABLE BLOCKINGS USED FOR CHAINS REMOVAL SHOULD BE
USED TO SUPPORT MAST SECTION DURING DISASSEMBLY.
NOTE: Unless the pulley supports need replacing, there is
no need to remove the lifting chains for removing the
pulleys. If the pulley supports need replacing, follow
the lifting chain removal and installation procedure.
Once the chains slackened, only remove the long
anchor to be able to run the chain out of the pulley
support (if necessary).
Rotate the turntable to the left to get an easier access to
the mast assembly and to be able to install supports for
the mast sections.
Pulley Removal
1.
Follow the lifting chains removal and installation pro-
cedure to install blockings under the appropriate
mast section(s).
2.
Remove the locknut from a long anchor and loosen
the attachment nut to slacken the chain.
31210090
SECTION 5 - TURNTABLE AND VERTICAL MAST
3.
Remove the hardware securing the pulley support to
the mast and slide the pulley support out of the
mast.
Figure 5-47. Pulley Support Removal
4.
Remove the pulley pin locking hardware and drive
the pin out while holding the pulley.
Pulley Installation
1.
Position the chain over the pulley. Align the pulley
with the mounting holes in the pulley support and
install the pin. Secure the pin with hardware.
2.
Install and secure the pulley support to the mast.
3.
Tighten the attachment nut of the long anchor to ten-
sion the chain before removing the other pulley sup-
port. The locknut will be installed after chains
tension adjustment procedure.
4.
Remove blocking as described in the lifting chains
installation procedure and adjust chains tension
accordingly.
5.8 MAST CYLINDER REMOVAL AND
INSTALLATION

Mast Cylinder Removal

1.
Place the machine on a flat and level surface.
Remove chassis hoods and chassis side shield.
Rotate the superstructure 90° to the right.
2.
Using the ground controls, fully raise the mast.
3.
Install a couple of suitable blocking to support mast
section #2 as indicated below.
– JLG Lift –
5-25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Toucan 20eToucan 10eToucan 26e

Table of Contents