Test run

After installation or inspection, carry out a test run:
1. Start up the machine without a load. To do this, close the circuit breaker and do not switch
off prematurely. Check whether it is running smoothly.
Switching the machine off again while it is starting up and still running at slow speed
should be kept to a bare minimum, for example for checking the direction of rotation or
for checking in general.
Allow the machine to run down before switching it on again.
2. If the machine is running smoothly and evenly, switch on the cooling equipment. Continue
to observe the machine for a while in no-load operation.
3. If it runs perfectly, connect a load.
1LE5, 1PC4 shaft height 315/355
Operating Instructions, 10/2020, A5E41454666A
NOTICE
Thermal overload of motors connected directly to the line supply
In addition to the load torque, the ramp-up (accelerating) time is essentially influenced
by the moment of inertia to be accelerated. While ramping up when connected to the
line supply, the inrush (starting) current is a multiple of the rated current. This can result
in thermal overload. This can damage the motor.
As a consequence, when ramping up, observe the following:
• Monitor the ramp-up time and number of consecutive starts.
• Comply with the limit values and/or ramp-up conditions specified in the catalog or the
order documentation.
Commissioning
7.2 Switching on
79

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotics sd 1pc4

Table of Contents