5.4 Connecting and Terminating the Vent Pipe

Refer to the following example to install the common vent system. The installation area should be measured to
ensure that sufficient space is available to install the water heater units and the common vent system. Ensure that
the common vent system is installed near the water heater units while satisfying all clearance requirements that
are specified in this manual as well as the Installation Manuals supplied with the water heater units.

5.4.1 Connecting the Main Pipe Runs to Wye Joint or Wye Assembly

After connecting the wye joint or wye assembly, connect the main trunk pipe to each side of the wye joint or wye
assembly. Each trunk pipe is connected to the other wye joint or wye assembly. Refer to "Connecting Pipes with
Cement" on page 67 for more information.
DANGER
If the connections leak, harmful flue gas may cause personal injury or death. After completing the installation
and filling the water heater with water, turn on the water heater and test for leaks using a bubble test kit. After
applying the soap solution, bubbles will form on the connection if any leaks exist.

5.4.2 Installing the System Termination

End caps, pipe elbows or tee joints can be used at the open ends of the intake and exhaust vent pipes. Refer to the
following installation examples that depict how the parts are fitted at the end of the common vent system piping.
The illustration is intended for reference purposes only.
Note
End Cap
Field Supplied Termination
Screen (Optional)
Installing a Common Vent System
75

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Npe-210a2Npe-240a2Npe-150s2Npe-180s2Npe-210s2Npe-240s2

Table of Contents