For installations where the unit is mounted directly on the inside of an external wall.
This installation requires a 2° fall from the heater connection to the wall terminal to
drain condensate and wind blown rain—the Arriva Direct A and B flue kits have an
inbuilt 2° fall.
Direct flueing using the Direct A and B flue kits - ARRIVA models only
Before starting, create the wall penetration. The minimum diameter required is 80 mm to non-
combustible surfaces such as brick, and 100 mm to combustible surfaces such as plaster.
1. Disassemble manifold
The flue consists of three parts;
sleeve, inside connections and
tube, and outside terminal.
Disassemble by pulling hard on
the outside terminal and inner
connections, then pull the sleeve
off the outer terminal.
Sleeve
Terminal
Connection
4. Fix sleeve
Fix the sleeve to the wall using the
three screws provided. The flange
is marked 'TOP'. The sleeve must
be fitted with this mark up. Check
sleeve protrudes 5-10 mm on the
outside.
5-10mm
"TOP"
Fixing Screw
Don't remove green plastic covering from sleeve.
7. Attach ties
Pull hard on the LH and RH ties,
and clip ties over the lugs inside the
sleeve. You should be able to pull
the ties two or three slots past the
starting point. Cut the ties approx.
20 mm past the lugs and bend so
they are parallel with the wall.
Cut (leave 20mm free)
Pull hard
Fixing tie Lug
Sleeve
Terminal
2. Adjust flue length
Measure the wall length through
the drilled hole. Adjust the sleeve
length to the wall thickness
plus 5-10 mm (required sleeve
protrusion from wall).
Do not extend beyond red line
Extension joint under plastic
Extension
(A flue only)
Adjust length by turning sleeve
5. Check and add rubber seal
Check the rubber seal is in place
on the terminal. For weatherboard
walls, add the spare rubber seal
provided to compensate for the
weatherboard angle.
Terminal seal
(add weatherboard
seal here)
8. Insert inner connection
Push the inner connection
assembly into the terminal tube.
Ensure correct positioning—refer
'TOP' mark. Fix with the three
screws provided.
Top mark
Screw
lnner
connections
3. Remove flue extension
For 'A' flues, depending on wall
thickness, the flue extension may
need to be removed. There is no
extension on the 'B' flues, they can
be fully adjusted by turning the
threaded section.
Do not extend
beyond red line
Extension joint
under plastic
Adjust length by turning sleeve.
6. Install terminal
From the outside insert the terminal
into the sleeve with the 'A' mark at
the top.
The LH fixing tie is marked 'LEFT'
(from the inside)
Label
Fixing tie
9. Adjust manifold
Adjust the manifold as required.
The manifold can still be turned
after attaching.
Outlet
Inlet
Arriva/Evolve flue installation guide: 10726-I 09-21 | 13
Extension
("A" flue only)
"TOP" mark "A"
Terminal
Rubber cap

Advertisement

Table of Contents
loading

This manual is also suitable for:

Evolve

Table of Contents