Manual Ir Target Calibration Process - Fluke 4180 Technical Manual

Precision infrared calibrator
Hide thumbs Also See for 4180:
Table of Contents

Advertisement

4180, 4181
Technical Guide
Intra-Test DUT Settings
Once all necessary As Found data is collected, but before you do the alignment, the DUT configuration
and control settings must be set to the indicated values in Table
alignment process is performed as required.
Setting
Integral
Derivative
Prop Band
Post-Test DUT Settings
Once the calibration process is complete and all As Left data has been collected, the DUT
configuration and control settings must be set to the indicated values in Table
ready for use.
Setting
Value
Cal Date
<today>
Set-
25
point
Scan
<value>
Rate
Stable
DEF
Limit
Soft
<value>
Cutout

Manual IR Target Calibration Process

The Product is tested and calibrated with the tests outlined below in the sequence indicated,
see Table 8. Details to do each of the tests can be found in the subsequent section of this
document.
Many tests that use the same nominal set-points may be done sequentially as noted. For test
specifications, durations, soak times, and other detailed information, refer to the specification
tables in the Operators Manual.
All temperature tests are to be done in °C. Before you start any tests, make sure the system
temperature units are set to °C.
48
Table 6. Intra-Test Controller Settings
Value
DEF
PID controller integration time setting
DEF
PID controller derivative time setting
DEF
PID controller proportional band setting
Table 7. Post-Test DUT Settings
Set calibration date to today (only if IR target alignment
performed)
Set set-point to 25 °C
Set scan rate to the value defined for the instrument use
Set stable limit to the value defined for the instrument use
Set soft cutout to value defined for the instrument use
6
to ensure the data collection and
Description
Description
Note
7
to ensure the DUT is