Chapter 5 – Commissioning the Drive Section

Overview

Installation Checklist
Check that the mechanical and electrical installation of the
frequency converter is inspected and OK.
Ensure that the insulation resistance of the assembly is
checked according to the instructions.
Ensure that the surroundings and inside of the cabinet is
free from dust and loose objects (like cable trimmings and
other waste left from the installation).
ACS 600 MultiDrive
This chapter describes the hardware commissioning of an ACS 600
MultiDrive drive section. For the drive control firmware commissioning
refer to the application program Firmware Manual (for System,
Standard, Crane Drive or other Application). For supply section
commissioning refer to Supply Sections User's Manual (DSU, TSU or
ISU).
WARNING! The work described in this chapter must only be carried
out by a qualified electrician. The Safety Instructions on the first pages
of this manual must be followed. Negligence of the safety instructions
can cause injury or death.
The installation must be checked before commissioning the Drive
Section.
Action
Information
See Chapter 4 – Installation
Checklist.
See Insulation Checks in
Chapter 3.
After the start, the cooling air
fans may suck nearby loose
objects into the unit. This might
cause failure and damage the
unit.