Integrated Pump Package (Optional)

Installation – Mechanical
On chiller sizes 090, 105 and 125 standard effi ciency; the suction pipe is not installed on the pump fl ange for shipping
purpose. This operation will have to be done once the chiller is delivered on job site according to the following fi gure.
Fasteners and gaskets are fi xed to the pipe assembly.
Figure 9 – Shipping arrangement and Operational arrangement
The heater cable will be routed along the frame cross member to be connected to the heater terminal block located
inside the junction box according to the following fi gure.
Figure 10 – The junction box