5 Installation and Commissioning
5.1 Installing the hardware
Installation and Commissioning
5
5.1
Installing the hardware
The necessary hardware components are listed in
Note
The installation guidelines of all components have to be observed.
NOTICE
Before you switch on the power supply, complete and check the
installation!
5.1.1
Hardware setup of the remote station
The figure below shows the hardware setup of the remote station with the central
station and the engineering station.
Figure 5-1
CP 1242-7
GPRS V2
Industrial Ethernet
Table 5-1
No.
1.
2.
3.
4.
5.
6.
7.
TeleService with TCSB
Entry-ID: 56720905,
V1.0,
CPU 1217C
24 V
192.168.0.1
Insert your SIM card into the CP 1242-7 GPRS V2.
Connect the individual modules to a suitable module rack.
Connect the CPU with the CP 1242-7 GPRS V2.
Connect the antenna to the CP 1242-7 GPRS V2.
Connect the engineering PG to the PROFINET interface of the S7-CPU.
Note:
This connection is only required while the project data are loaded. Remote
maintenance occurs via the Internet.
Connect the CPU 1217C and the CP 1242-7 GPRS V2 to a 24 V DC power
source.
Connect the DC power source to the power grid
(230 V AC).
10/2016
Chapter
2.2.
Programming Unit
192.168.0.100
Action
20