Prestart Installation Check - Kohler 12RESV Installation Manual

Residential/commercial generator sets
Hide thumbs Also See for 12RESV:
Table of Contents

Advertisement

1
1. To positive (+) terminal on starter solenoid.
2. To ground (--) terminal on or near starter motor.
Figure 1-27 Typical Battery Connection
Use the following procedure to install and connect the
battery.
Battery Installation Procedure
1. Ensure that the starting battery is fully charged
before placing the battery in service.
2. Clean the battery posts and/or adapters if
necessary.
3. Install the battery post adapters, if needed.
4. Place the battery in the housing.
Note: Ensure that the battery is positioned toward
the front of the generator so it does not block
the
alternator
Figure 1-5.
5. Connect the positive (+) lead to the engine starting
battery.
6. Connect the negative (--) lead to the engine starting
battery.
Refer to the generator set operation manual and the
battery
manufacturer's
maintenance instructions.
When power is applied to the RDC2/DC2 controller (that
is, when the battery is connected), you will be prompted
to set the date and time, and then to set the exerciser.
See Section 1.13 and the generator set operation
manual for instructions.
If the battery is disconnected for service or replacement,
the exercise settings on the RDC2/DC2 controller are
lost. Set the exerciser after installing and connecting the
battery. See Section 1.13, Set Exerciser.
TP-6984
5/17a
2
EZ-273000-J
air
intake
vent.
See
instructions
for
battery

1.12 Prestart Installation Check

Review the entire installation section. Inspect all wiring
and connections to verify that the generator set is ready
for operation. Check all items in the following Prestart
Checklist.
Prestart Checklist
Air Cleaner. Check that a clean air cleaner element is
installed to prevent unfiltered air from entering the
engine. See the generator set operation manual for
instructions.
Air Inlets. Check for clean and unobstructed air inlets.
Battery. Check for tight battery connections. Consult
the battery manufacturer's instructions regarding
battery care and maintenance.
Enclosure. Check that all enclosure panels and internal
baffling are in place.
Exhaust System. Check for exhaust leaks and
blockages. Check the muffler condition.
Inspect the exhaust system components for cracks,
D
leaks, and corrosion. Check for tight exhaust system
connections.
Check for corroded or broken metal parts and replace
D
them as needed.
Check that the exhaust outlet is unobstructed.
D
Oil Level. Maintain the oil level at or near, not over, the
full mark on the dipstick.
Operating Area. Check for obstructions that could
block the flow of cooling air. Keep the air intake area
clean. Do not leave rags, tools, or debris on or near the
generator set.
Section 1 Installation
29

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

8resv10resv12resvlRdc2Dc28resvl ... Show all

Table of Contents