Periodic Maintenance
Contractor Confirmation Check
Sheet
This check sheet must be completed by the installing
FWD
contractor and submitted prior to requesting Trane
Power supply
Service start-up support. The check sheet identifies a
Capacities
list of items that need to be completed prior to actual
Cooling capacity on water (1)
machine start-up.
Heating capacity on water (2)
Fan motor
Fan power input (3)
Current amps (3)
Start-up amps
Air flow
Addressed to the Trane Service office of:
minimum
nominal
Job Name:
maximum
Model No.:
Main coil
Water entering/leaving connections
Unit
Electric heater (accessory for blower only)
❏ Unit installed
Electric power supply
Heating capacity
❏ Isolator pads in place
Hot water coil (accessory for blower only)
Heating capacity (4)
Chilled Water
G2 filter (filter box accessory)
Quantity
❏ Connected to the unit
Dimensions ( LxWxth)
G4 filter (filter box accessory)
❏ Connected to the air handling units
Quantity
❏ Connected to the pumps
Dimensions ( LxWxth)
Condensate pump (accessory)
❏ System flushed and then filled
Water flow - lift height
Not available for FWD30 and FWD45
❏ Pumps run and air bled
Sound level (L/M/H speed)
Sound pressure level (5)
❏ Strainers cleaned
Sound power level (5)
Unit dimensions
❏ Flow switch installed and checked/set
Width x Depth
Height
❏ Throttling cock installed in leaving water
Shipped unit dimensions
❏ Thermometers installed in leaving/entering water
Width x Depth
Height
❏ Gauges installed in leaving/entering water
Weight
Colour
Recommended fuse size
Unit alone (aM/gI)
Unit with electric heater (gI)
(1) Conditions: Water entering/leaving temperature: 7/12 °C, Air inlet temperature 27/19°C DB/WB - Nominal air flow
(2) Conditions: Water entering/leaving temperature: 50/45 °C, Air inlet temperature 20°C DB - Nominal air flow
(3) At high speed with nominal air flow.
(4) Water entering/leaving temperature 90/70 °C, air inlet temperature 20 °C DB, Nominal air flow.
(5) A rectangular glass wool duct 1m50 long is placed on the blower.The measurement is taken in the room containing the blower unit.
Heat exchanger operating limits:
We will therefore require your service technician on job by*_____________________.
FWD:
*water temperature: max 100° C
*absolute service pressure: min 1 bar/max 11 bars
Checklist completed by____________________________________________________.
Accessories - Hot water coil:
*water temperature: min. +2° C/max. 100° C
*absolute service pressure: min 1 bar/max 11 bars
Date____________________________________________________________________.
* Return this completed checklist to your Trane Service office as soon as possible to enable the start-up visit to
be scheduled. Be aware that advance notification is required to allow scheduling of the start-up as close to the
requested date as possible. Additional time required to complete the start-up and adjustment due to incompleteness
of the installation will be invoiced at prevailing rates.
4
40
Technical Data
08
(V/Ph/Hz)
(kW)
5,2
(kW)
6,3
(type)
(kW)
0,23
(A)
1,1
Contractor Confirmation Check Sheet
(A)
3,2
(m
/h)
490
3
(m
/h)
820
3
Job location:
(m
/h)
980
3
Sales order No.:
(type)
Cooling water
(Dia)
3/4"
❏ Connected to the unit
(V/Ph/Hz)
230/1/50
(kW)
2/4
❏ Connected to the cooling device
(kW)
6,3
❏ Connected to the pumps
2
❏ System flushed and then filled
(mm)
386x221x8
❏ Pumps run and air bled
-
❏ Strainers cleaned
(mm)
-
(type)
❏ Flow switch installed and checked/set
(l/h - mm)
❏ Throttling cock installed in leaving water
(dB(A))
36/40/43
❏ Thermometers installed in leaving/entering water
(dB(A))
46/50/53
❏ Gauges installed in leaving/entering water
(mm)
890 x 600
(mm)
250
❏ Cooling water control operational
❏ Water treatment equipment
(mm)
933 x 644
(mm)
260
Wiring
(kg)
32
❏ Power supply connected and available
(A)
8/16
❏ External interlock connected
(A)
16 (2kW),25 (4kW)
Load
❏ System can be operated under load condition
12
20
230/1/50
8,3
15
11,9
18,9
2 x direct drive centrifugal
0,46
0,65
2,2
3,1
5,5
9,3
980
1400
1650
2300
1970
2600
ISO R7 rotating female
3/4"
1 1/2"
230/1/50 or 400/3/50
400/3/50
8
10
12
17,4
2
2
486x271x8
586x321x8
2
2
486x264x48
586x314x48
Centrifugal
24 - 500
38/41/44
46/50/53
48/51/54
56/60/63
1090 x 710
1290 x 820
300
350
1133 x 754
1333 x 864
310
360
46
61
galvanised steel
8/16
8/16
40 (230V),3*16 (400V)
3*20
30
45
18,8
30,1
20,9
38,2
1,04
1,51
4,7
5,5
14,1
16,5
1800
2700
3000
4500
3600
5400
1 1/2"
1 1/2"
400/3/50
400/3/50
12
12
22,4
34,5
2
2
586*421*8
586*621*8
2
2
586*414*48
586*614*48
47/52/57
47/52/58
57/62/67
57/62/68
1290 x 970
1290 x 1090
450
650
1333 x 1008
1333*1133
460
660
76
118
8/25
8/25
3*25
3*25
UNT-PRC002-GB
RLC-SVX023A