ID3000 Series Installation & Commissioning Manual
5.5 Zonal LED & Printer Options
The section describes the procedures for fitting zonal
LED modules and the integral PRN-ID printer. One or
two extension chassis are required to provide the zonal
LEDs required with or without the integral printer. The
following options are described in this section:
a. LEDs for up to 64 Zones. For panels with up to 64
zonal LEDs follow the instructions in Section 5.5.1.
b. LEDs for up to 128 Zones (as 'LEDs for up to 64
zones' x2, with a double-extended back box).
c. Fitting the PRN-ID Printer. The integral PRN-ID printer
can only be fitted with the extended or double-extended
back boxes. An extension chassis is required, either with
zonal LEDs 1-64 or with a blank fascia if these zonal LEDs
are not required. Refer to Section 5.5.2.
d. LEDs for up to 256 Zones. For panels with up to 256
zonal LEDs refer to Section 5.5.3. For this option the double-
extended back box and 256 Zone LED Kit is required.
Note: All fitting instructions assume that the correct back
Taking suitable anti-static precautions, such as wearing
a grounded wrist strap, remove all packaging and inspect
for any damage that may have occurred in transit. If no
damage is evident, proceed with these instructions.

5.5.1 64 Zone LED Extension Chassis

Before attempting this procedure, make sure ALL
power to the control panel is disconnected.
Fit the extension chassis (A) to the back box (B) as
follows:
1 Locate the four supplied M4 x 16 SEM screws (C) in the
2 Connect one end of the supplied, 10-way ribbon cable
3 Connect one end of the supplied earth lead (G) to the
4 With the extension chassis correctly orientated (refer
5 With the extension chassis now located on the back
6 Connect the other end of the earth lead to the earthing
26
box option has been installed in each case.
back box holes (D) and insert them approximately half way.
(E) to the top connector (F), marked 'IN', of the LED PCB
(also refer to the drawing overleaf).
earthing blade terminal (H) on the extension chassis.
to drawing at left), locate the keyholes onto the four
screws with the threaded part in contact with the top
flats of the keyholes.
box, open the main chassis front door and connect
the other end of the 10-way ribbon cable at socket
SK19 on the Base PCB.
blade terminals located inside the back box and to the
right of the chassis.