Overview Of The Steps To Be Taken And The Maintenance Report - Wolf CGB-35 Maintenance Instructions Manual

Gas fired condensing boiler

Advertisement

No.
Step
1
Switch OFF the boiler, switch OFF the emergency stop switch
2
Close the gas supply valve,
3
Remove the casing and the combustion chamber housing
4
Undo the gas fitting
5
Pull the electrical cables off the fan, sensors and electrodes
6
Remove the heat exchanger lid
7
Visual inspection of the burner unit
8
Check the ignition electrodes and replace if required
9
Clean the heating water heat exchanger
10
Clean the condensate pan
11
Check and replace gaskets, if required and lubricate the replace-
ments with silicone grease
12
Refill granulate, if a neutralising system is installed
13
Check the protective anode every 2 years on enamelled cylinders
and replace, if necessary
14
Assemble the boiler
15
Clean and fill the siphon, install and check for tight fit
16
Check the expansion vessel in case of water loss
17
Open the gas supply valve and start the boiler
18
Gas soundness test
19
Flue gas system soundness test
20
Check the ignition
21
Check the interaction with control accessories
22
Flue gas test in emissions test mode
23
Gross flue gas temperature
24
Air supply temperature
25
Net flue gas temperature
26
Carbon dioxide content (CO2)
27
or oxygen content (O2)
28
Carbon monoxide content (CO)
29
Flue gas loss
Confirm maintenance (company stamp, signature)
Date:
3061491_0805
Overview of the steps to be taken and the
maintenance report
Report item
O
O
O
O
O
O
O
O
O
O
O
O
O
O
°C
°C
°C
%
%
%
%
15