Installation (cont'd)
Skid Removal
Important: See lifting instructions to properly lift case
when being placed on dollies or permanent location.
(See page 6 for Lifting Instructions.)
Lifting Points
Leave all hardware and fi ttings in place until case is
located at or near its preferred location. Using forklift
or J-Bar lift the case from the skid and placing dollies
underneath each base leg, proceed to moving the
case to its designated location if not done so already.
Dollie Placement
The Illustration below demonstrates perfect place-
ment of a dollie per 1 side for both base legs of the
merchandiser.
Move the fi xture as close as possible to its perma-
nent location and then remove all packaging and
prepare to remove off Skid. Remove all separately
packed accessories such as kits, and panels. Check
for damage before discarding packaging.
Hardware Removal
Remove screws as well as fastened plates bolted to
skid at each base leg.
Remove fastened plates only upper base legs are to
remain fastened onto case.
Once the fastened plates are removed a J-Bar can
be used to lift at each end of the leg bases to remove
the below skid