2)
Temporarily attach the saddle on the meter run pipe using the U-bolt and associated hardware; do not tighten.
Screw the 2" mounting pipe into saddle. Place level against pipe and vertically align. Adjust the pipe, mounted in
3)
saddle, until vertical alignment is achieved.
After vertical alignment, securely tighten 2" pipe in saddle and then securely tighten saddle mounting bolts. Be certain
4)
pipe is securely installed in saddle.
NOTE: To install the XRC
position and the other to install and tighten the mounting brackets.
The method of installation must be consistent with customer's company policy.
on the 2" mounting pipe and secure in place with two U-bolts, flat washers, lock washers and two
G4
Position the XRC
G4
5)
Figure 27: XRC
pipe mounting.
See Figure 28 through Figure 30 for final installation dimensions.
Saddle
"U" Mounting
Bolt
Figure 26: Typical pipe saddle installation
G4
, it is recommended that two people perform the installation: One to hold the unit in
9/16" bolts as shown in
Flat and lock washers
with nut
Figure 27: XRC
2" x 40"
Mounting Pipe
Meter Run
U - Bolt
2 " Mounting Pipe
G4
pipe-mounting
XSeriesG4 Remote Controller User's manual 2103334 Rev. AB | 27
2 Installation