The function test must be carried out in accordance with EN 54-16, section
16.2, 'Function tests'.
Perform the function test on site at the same time as the system acceptance
test.
If the system is connected to a fire detection installation (FDI), the function test
must be performed with the FDI connected.
You can test the required visual and acoustic indicating elements according to EN
54-16 by operating them manually in access level 1 or 2 in accordance with the
configuration of the VACIE.
Check the display and LED for any indication of shutdowns if corresponding
devices are part of the system.
Check the display by pressing the <Buzzer reset/test – acknowledgment/test>
button on the PT2004 and 2007.
Check the keypad functions.
A full acceptance test must be performed after every time a change is made to
the system.
Testing interval
All indicating elements must be tested every six months.