Rheem Solar Hiline 52D180 Owner's Manual And Installation Instructions page 49

52d series open circuit
Hide thumbs Also See for Solar Hiline 52D180:
Table of Contents

Advertisement

INSTALLATION CHECKLIST
Prior to handover, complete the final check list:
1.
System is installed as per the installation instructions ............................................................................ [
2.
Potable water is connected, turned on and solar storage tank is filled ................................................... [
3.
All mechanical fixings are secured .......................................................................................................... [
4.
Collectors have correct kick (12-15 mm per collector) ............................................................................ [
5.
Protective plastic film removed from tank (if fitted) ................................................................................. [
6.
Covers removed from collectors .............................................................................................................. [
7.
Pipe, conduit penetrations through the roof have been sealed correctly ................................................ [
8.
Roof tiles put back into position ............................................................................................................... [
9.
Roof flashing watertight ........................................................................................................................... [
10. System checked for water leaks and pipe connections are correctly tightened ...................................... [
11. Cold and hot water piping checked for water leaks ................................................................................. [
12. Drain pipes free of any obstruction .......................................................................................................... [
13. All pipe work clipped where necessary ................................................................................................... [
14. Electrical power to the booster is switched on (if required) ..................................................................... [
15. Operation of booster checked ................................................................................................................. [
16. Air bled from taps .................................................................................................................................... [
17. Owner has been instructed on use and has been given this booklet ...................................................... [
49
COMMISSIONING
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Solar hiline 52d300

Table of Contents