1.1.5 Inspecting and Unpacking Each Cabinet

The first task in preparing for installation is inspecting and unpacking the UPS. The UPS
and accessory cabinets are shipped bolted to wooden pallets, as shown in Figure 1
protected with outer protective packaging material.
Figure 1–1. Powerware 9335 (80 kVA and 120 kVA) UPS Packaging
Powerware 9335 (80 kVA and 120 kVA) Installation and Operation
164201396 REV A 071103
1, and
NOTE: Packed
inside the shipping
carton on top of
the UPS cabinet is
an accessory
carton containing
the metal grilles to
be installed at the
unit base after it is
fixed in the final
position. Remove
this box from the
cabinet before
moving UPS to its
final position