Commissioning
2.5 Initial commissioning using servo (booksize) as an example
Figure 2-8
Signal flow for initial commissioning example (servo; part 2)
2.5.4

Commissioning with Starter (example)

The table below describes the steps for commissioning with STARTER.
Table 2-5
Sequence for commissioning with STARTER (example)
What to do?
1.
Automatic
configuration
62
How to do it?
Operator action:
-> "Project" -> "Connect to target system"
-> Double-click "Automatic configuration"...-> Follow the
instructions provided in the Wizard.
Commissioning Manual, (IH1), 07/2007 Edition, 6SL3097-2AF00-0BP7